1.5 Billion Euros in Construction Tenders Over Five Years and 2,500 Contract Amendments: Won on One Set of Terms, Built on Another

1 min read
Share

Over five years, from 2021 to 2025, public institutions signed 9,335 construction contracts worth 1.5 billion euros. Those contracts were amended 2,500 times. That's the figure behind the headline of the new research by the Center for Civil Communications: tenders "are awarded under one set of terms and carried out under another".

The pattern is familiar and needs little explaining. The tender is won with one price and one deadline. Then, as the work goes on, deadlines get extended, the value grows, and the scope and terms change. According to the research, this practice cancels out the whole point of a tender and raises the risk of collusion, corruption and abuse.

More money, less competition

The value of contracts grows year after year, but there are fewer and fewer bidders. In 2021 a tender drew five bids on average; in 2025, only three. The value of contracts awarded without competition, with a single bidder, rose three and a half times: from 38 million euros in 2021 to 141 million euros in 2025.

Over five years, ten construction firms won tenders worth around half a billion euros, almost a third of all the money spent on construction work. Among them are "Stenton Gradba" from Bitola, "Zhikol" from Strumica, "Ilinden" from Struga, "Granit", "Bauer BG", "Ju-Baj 2", "Bitem", "Lendi Grup" and "Zobek Mining" from Skopje, and "NB-Kompani" from Tetovo. The CCC calls that kind of concentration a red flag that calls for further scrutiny.

How does the circle get narrower? Through the conditions. Multiple and highly specific references, precisely pre-defined staff, exactly listed equipment, in-house laboratories, in-house asphalt and concrete plants. A tender that anyone can formally apply for, but that in practice only a handful can meet.

Who supervises the supervisors

The most awkward part is supervision. Just 10 companies account for 91 percent of the value of construction supervision contracts, and only two of them for over 61 percent. These are the firms that are supposed to confirm the contractor did the job properly. According to the research, supervision is increasingly reduced to formally signing off whatever is on the ground. Bank guarantees and contractual penalties are rarely used, and defects in completed works often show up soon after they are finished.

For a significant share of projects, even their status can't be determined with certainty, because the number of contracts signed and the number of completion notices in the electronic system differ widely. And one more detail: in election years, especially before local elections, the value of construction tenders is significantly higher.

Which ministry, which inspectorate or which prosecutor's office will read this research and open even one of those 2,500 annexes?