Expert witness at the Puls trial: the change-of-use application had to come from the owner, not the tenant
26.08.2026
26.08.2026
26.08.2026
26.08.2026
26.08.2026
26.08.2026
26.08.2026
26.08.2026
25.08.2026
24.08.2026
26.08.2026
26.08.2026
25.08.2026
26.08.2026
26.08.2026
26.08.2026
26.08.2026
25.08.2026
24.08.2026
26.08.2026
26.08.2026
26.08.2026
26.08.2026
26.08.2026
25.08.2026
09.03.2026
27.02.2026
19.02.2026
26.08.2026
25.08.2026
24.08.2026
23.04.2026
23.04.2026
12.04.2026
There is one moment in the Idrizovo courtroom worth more than four hours of cross-examination. The lawyer for Grozdan Milkovski, owner of the building that housed Puls, was steering the expert witness toward the answer she needed: in 2012, when she leased it out, the building was a production plant, safe and up to code. The expert confirmed it. Then came the next question, and the answer that took the whole construct apart.
"Under the Construction Act, an application to change a building's use must be submitted by the owner of that building," said Goran Markovski, professor at the Faculty of Civil Engineering at UKIM and one of the prosecution's most important witnesses. The owner. Not the tenant. Not whoever fitted polyurethane foam under the ceiling. The one whose name is on the paperwork.
A private contract is not the law
The defence tried to route around that through the lease, which contains a clause saying the tenant obtains the documents required for the business. Markovski did not budge. Agreements between parties, oral or written, do not override the Construction Act. "On the basis of that internal contract of theirs the municipality cannot issue an approval, it needs either a power of attorney or the owner in person," the expert said.
That is the key to the entire case, delivered in one sentence. Twenty-one people can divide responsibility among themselves on paper, but the state recognises only one signature. And that is where it becomes clear why the question of who had to file the application is not a technicality - it is the difference between a building that passed inspection and a building no inspector ever entered.
The inspector who had both the right and the duty
The second part of the expert report lands even closer to the institutions. Asked whether a building inspector can act on his own initiative once a building is in use, with no reconstruction work reported, Markovski was explicit: the inspector not only has the right but the obligation to act after construction too, on any change of use, extension or alteration.
"The fate of a building, from the issuing of the construction permit right through to its demolition, falls under the building inspector, regardless of what activity is carried out inside it," the expert stressed. Two municipal building inspectors from Kočani are among the defendants.
The report does not rule on the cause of the fire, but it does on how it spread: "The rapid spread of the fire is a direct consequence of the choice of unsuitable construction materials." Acoustic insulation foam, in a building never designed to be a nightclub.
The questions nobody is asking
During the break, the parents of those killed came out with a statement that describes the situation better than any legal commentary. "From today's hearing one thing becomes ever clearer: the essential questions seem to be the hardest ones to ask," said Aleksandar Naunov. Instead of precise questions that would test the findings, they listened to long runs of repetition and returns to what had already been said.
"We will sit and listen for as long as it takes, because behind this trial there are not just piles of documents and expert reports - there are 63 lives that ended and families who live the consequences every single day. Facts are refuted with facts, expert findings with arguments, and time, evidently, with questions without end," he added.
The prosecution is run by a team of 15 public prosecutors, the proceedings are chaired by judge Dijana Gruevska-Ilievska, and the case is still in the evidentiary phase. Once the construction experts have been examined the prosecution is due to close its case, and then the defence begins. The next hearing is on 1 September.
The trial is necessary, and it means something only if what comes out of it is an answer bigger than a chart of signatures. Until then, one sentence from today's hearing is worth holding onto: a building inspector's duty does not end when the building goes up. It did not end when the plant became a nightclub either.
The latest 10 news from this category
Eight years of cash payouts booked as "travel expenses", with not one document behind them. The calculation, down to the...
Twenty-three fires in a single day, aircraft redirected from one front to the next. And on Kitka, someone waits for...
Three hundred fewer classes, twenty-six villages without a school. Janevska says they "managed" to do it - but an empty...
A boat hit a paddleboard just off the shore, and the response came from residents standing on boards in the...
Tetovo Clinical Hospital sits under the health ministry. The director says there is nothing political about it - and in...
The fire is not being put out - it is being buried under soil. And when clearing a dump means...
One suspected case was enough for an entire village to be treated. Spraying is protocol and it has to happen...
The municipalities are doing more than they have to. The problem is that "free education" means the teaching is not...
Reactors worth tens of billions of dollars, but the signature is being demanded somewhere else entirely. When energy becomes the...
The Secret Service confirmed it is aware of the footage. When the target is not the politician but his family,...
This site uses cookies - is that okay? Learn more
Be the first to know when Metla launches something new
Leave your email and we will write when there is a new guide or something new on Metla.