They Rode In on Scooters, Torched the Shops and Left: The Fire in Shuto Orizari Burned for Three Hours, Setting It Took Fifty Seconds
13.09.2026
13.09.2026
13.09.2026
13.09.2026
13.09.2026
13.09.2026
13.09.2026
13.09.2026
12.09.2026
11.09.2026
13.09.2026
13.09.2026
12.09.2026
13.09.2026
13.09.2026
13.09.2026
13.09.2026
12.09.2026
11.09.2026
13.09.2026
13.09.2026
13.09.2026
13.09.2026
13.09.2026
12.09.2026
09.03.2026
27.02.2026
19.02.2026
13.09.2026
12.09.2026
11.09.2026
23.04.2026
23.04.2026
12.04.2026
"Two galleries are fully finished, work on the third is intensive. We are opening another 10 kilometres of motorway to traffic soon," Deputy Prime Minister and Transport Minister Aleksandar Nikoloski wrote on Facebook, posting video from the construction site on the Kichevo - Ohrid motorway. The sentence has everything except one thing - a date.
That "soon" is the whole difference for the thousands of drivers who right now, in the middle of the tourist season, are travelling to Ohrid and Struga through diversions. No precise chainage was published, no exact start and end point, no calendar date for when the section will open. The public got a political announcement, not an operational map.
Where exactly the work is
Judging by the site visit location, the new section runs on the Kichevo end, from the area above Kichevo towards the entrance to the tunnels under Preseka. Along that stretch, three galleries, two bridges, a stabilised slope and the entrance to the tunnel system have been built or are under construction. The three galleries together are about 1.1 kilometres long. More broadly, eight protective galleries are planned from Kichevo to the tunnels, their job being to shield the alignment from unstable slopes, rockfalls and landslides - one of this project's main problems for years.
The tunnel under Preseka has two separate bores, one about two kilometres long, the other about 2.1. Once open, they should be the longest road tunnel bores in the country. At Botun the engineering solution is different: some of the works need to go up to 21 metres into the ground to secure the unstable slopes.
Numbers that do not match
This is where it gets awkward. During the site visit at Preseka it was stated that eight galleries are spread from Kichevo to the tunnel entrance, with another six galleries or similar systems planned at Botun. The Public Enterprise for State Roads, meanwhile, said in separate official information that six galleries and eight retaining walls are being built on the motorway.
This does not necessarily mean the figures contradict each other - they probably refer to different phases or construction fronts. But on a project worth hundreds of millions of euros, a citizen should not have to reconstruct from three statements whether six, eight or fourteen galleries are being built and where each of them is. A single public map marking all this does not exist.
The same problem applies to the mileage. The state roads enterprise says that in 2025, in three phases, 13.5, 12.34 and a further 2.12 kilometres were opened on the Vrbjani - Botun and Klimeshtani - Ohrid stretches, totalling 27.96 kilometres. In the latest announcement the minister said drivers are already using 34 kilometres. The six-kilometre difference was not explained.
Even after the new 10 kilometres, the machines stay
Alongside the construction, the Preseka pass and the Izvor - Vrbjani and Botun - Klimeshtani sections are being rehabilitated, 15.1 kilometres in total. That is a separate project worth around 6.5 million euros, with a completion deadline of October 2026. So even when the new kilometres open, the altered traffic regime is not going to disappear from this corridor.
The Automobile and Motorcycle Association reports again today that traffic on the Kichevo - Ohrid route is running with diversions due to construction work on several sections, recommending adjusted speed. What the daily bulletin does not contain is the exact start and end point of each diversion, or the expected additional travel time.
The Kichevo - Ohrid motorway will be good news the day it opens. Until then, the ask is modest: one updated map, one chainage, one date. If the project really is on schedule, those are three things that cost nothing to publish.
The latest 10 news from this category
The deficit target raised from 3.5 to 4.1 percent of GDP, spending growing faster than revenue, and the growth forecast...
On euro loans with a variable rate, the rise comes due at the next reset. On fixed ones, it does...
The agreed price for first class is 40 denars. At the collection points they pay 15 to 18. Across the...
A Skopje company owes 14.87 million euros and there is nothing to recover it from. In one month the total...
223,711 tourists and 795,083 overnight stays in July. Turkey still leads with 50,955 guests, but its number fell by 7.6...
When the two biggest firms in an industry ask for rules on how fast anyone may run, the rules rarely...
Not a single password fell. What fell was the assumption that a request from a government domain is automatically a...
The board voted, the founder kicked the administrators out of Slack and held out for three days. What does a...
An announcement is not an adopted tariff. A lower bill is good news only if its cost has not been...
The Balkans have a long tradition of producing something valuable and selling it under someone else's name. The difference between...
This site uses cookies - is that okay? Learn more
Be the first to know when Metla launches something new
Leave your email and we will write when there is a new guide or something new on Metla.